Pickguard Installation

April 2013 No Comments

Step 1: The installation of the loaded pickguard is simple. You need to run the tremolo ground wire through the left side hole and run the black and white output wires to the jack area.

In some cases is wire that directly screws into the guitar body under the pickguard.

Step 2: Next just screw the pickguard onto the body. Over tightening the screws can strip out the wood.

If you still have to install your pickups, check out the Wiring Guide.

Step 3: Now is also a good time to install the strap buttons.

 

Next: Output Jack Installation